Narrative Description of Project:
Consisted of the provision of complete infrastructure: water supply system, electrical distribution networks, roads and drainage, sewerage and sewage disposal for housing estate with a population of 5000. Electrical services comprised the construction of 11/0.415kV 800kVA transformer substation, 100km of low voltage distribution network and associated service connections to housing units. The cost of the project was ¢3.6 billion and was financed by the World Bank.
|